City Plans to Streamline Building and Land Use Approval in ‘Get Stuff Built’ Taskforce Report

Client memorandum | December 21, 2022

Authors:  Anita W. Laremont, Zachary Bernstein and Aaron D. Kahen

The office of Mayor Eric Adams has released an initiative, termed “Get Stuff Built,” which aims to streamline portions of the land use review and construction processes. These changes focus on implementing improvements in three areas: (1) the City Environmental Quality Review process (CEQR), (2) the land use approval process, and (3) the Department of Buildings’ (DOB) permitting process.

  1. CEQR: CEQR is the review process by which City agencies evaluate the effects that a discretionary action, such as a zoning change, would have on the environment. The improvements to CEQR would exempt certain smaller projects from the environmental review process, improve the quality of the required analyses and create a web tool that will automate certain analyses.

Certain types of projects, such as housing developments potentially up to 200 dwelling units and shelters, would be exempt from CEQR analysis, and a number of analysis topics, including traffic analysis, would be streamlined.

  1. Land Use Approval Process: Applications for zoning actions can take many years because of the indefinite pre-certification stage of preparing an application in coordination with the Department of City Planning (DCP). The land use approval process would be modified to standardize and simplify application requirements and materials, limit rounds of review with DCP and create an express application review process for ministerial actions.

These actions, taken together, will shorten the time it takes to prepare applications for certification, thereby reducing project costs.

  1. DOB Permitting Process: Developers and homeowners must obtain the proper permits when constructing or altering new buildings, which can take a long time and require special expertise. The process to obtain these permits would be reformed by reducing DOB bottlenecks, facilitating interagency coordination when reviewing applications, and proposing legislation to fill in gaps in the building code, rules and local laws.

Specific improvements include making the DOB online permitting system more user-friendly and transferring the Fire Department’s construction permit responsibilities to DOB.

Due to the wide-ranging nature of the changes included in “Get Stuff Built,” the timeline for these improvements will vary. Some of the changes have already been made or will only require modifications and rule changes by City agencies, but others will require buy-in from City or State lawmakers.

Taken together with the Mayor’s “City of Yes” announcement in June and last week’s “New New York” plan issued by Governor Hochul and Mayor Adams, these initiatives signal the administration’s commitment to making it easier to do business.

We will continue to monitor these improvements closely and work with you to capitalize on them for the benefit of your projects.